Progress reports are common in engineering. As the name suggests, they document ongoing projects. They might be one-page memos or long, formal documents. Such a report is aimed at whoever assigned the project. Its goal is to enable the manager or sponsor of a project to make informed decisions about the future of the project.  Usually, progress reports are stressful. The sponsor wants a job done quickly and cheaply; the engineer needs to ensure accuracy and quality. A sponsor might cancel even a quality job if it is behind or overbudget. As the engineer, you need to please the sponsor and do the job well. Yet, any project of size or significance is bound to encounter snags: additional requirements, miscommunications, problems, delays, or unexpected expenses. A progress report must account for those snags. 


Organization

The original proposal for the project determines the structure: make use of original milestones or the timeline. With this in mind, the simplest structure is as follows: 

  1. Introduction
  2. Work Completed
  3. Work Scheduled
  4. Problems

But a more comprehensive list of components will give you a clearer structure, even if you return to the simpler structure for the report itself. 

Beer and McMurrey's [8] Detailed Structure: 

1. Introduction 
2. Project Description 
3. Progress Summary 
4. Problems Encountered 
5. Changes in Requirements 
6. Overall Assessment of the Project
This document adds:  7. Report Apparatus (titles, references, etc.) 


1. Introduction 
As always, first indicate the purpose of the report and its intended audience. Clearly define the time period covered in the report (see also titles). Then, explain the project's objectives and summarize the major issues. Sometimes the summary can be a separate section from the introduction [2]. 
 
2. Project Description 
In very short reports, the introduction might contain this section, but if it is under its own heading, readers who are familiar with the project can skip it. Someone unfamiliar with the project, however, needs summarized details such as purpose and scope of the project, start and completion dates, and names of parties involved [8]. Often this section can be adapted from a proposal or borrowed from a previous progress report. 
 
3. Progress Summary 
This is the substance of the report (so "summary" may be a misnomer). You want to discuss work done, work in progress, and work to be done. You might just use these as subheadings to structure the section. This would be a project-tasks approach. Other approaches are time-periods or a combined approach. 

Your project (and sometimes your sponsor) will determine which of these three you use. If the problems encountered or changes required are time-related, then use the time-periods approach to your advantage; likewise, if the problems or changes relate to specific tasks then use the project-tasks approach.  Another item that may be included here is a summary of financial data. This last item could be contained in a table or appendix, or an independent section. 
 
4. Problems Encountered 
As noted in the opening, snags are expected. Don't hide from them; explain what they are and how they might affect key areas of the job (such as timing, price or quality). If the problem occurred in the past, you can explain how you overcame it. This is least serious; in fact, you look good. If the problem is in front of you (now or in the future), explain how you hope to overcome it, if you can. 
 
5. Changes in Requirements 
Here, you record the changes to the project: milestones added, new requirements, or schedule changes (good or bad). Even if these changes have not affected the ultimate goal of the project, you need to tell the sponsor how problems have been accommodated. 
 
Note: If changes are a direct result of problems encountered, sections 4 and 5 may be combined. This would lead to a modified organization: first problem and the change it required, then the next problem and change, and so on. 

 
6. Overall Assessment of the Project 
Since a progress report is not about a finished work, the conclusion needs only to give your professional opinion of how the project is going.  Being unrealistically optimistic is as inappropriate as being unduly negative. Beware of promising early completion: a single setback can gobble up much time. Likewise, don't overreact if you are behind schedule. You may also gain time along the way. Far more significant for the engineer is to explain anything that may change the expected quality of the final product. Keeping in mind your purpose can help you focus here: your goal is to enable the manager or sponsor to make informed decisions. 

7. Report Apparatus 
A long progress report will include all the apparatus of formal reports: letter of transmittal, title page, table of contents, abstract, appendices, references. Only the most common will be addressed here. 